How to write a method statement
Method statements are widely used in construction as a means of controlling specific health and safety risks that have been identified (perhaps following the preparation of a risk assessment), such as lifting operations, demolition or dismantling, working at height, installing equipment, the use of plant, and so on.
A method statement helps manage the work and ensures that the necessary precautions have been communicated to those involved. Method statements should be written by a competent person who is familiar with the process being described and may need to be agreed between the client, principal contractor and contractor.
The first stage involves examining the work activity or process in question in preparation for writing the statement about it. The potential hazards of the work should be identified, including anything that has the potential to cause ill health or harm to anyone involved.
There should then be an analysis of what has been done to mitigate against these risks and whether the mitigation measures are sufficient. The guide term ‘As Low As Reasonably Practicable’ (ALARP) should be followed, and if necessary, further safety measures adopted.
The method statement typically begins with a header which contains important information for site staff and clients. This can include:
- The title of the job.
- The site address.
- Company name, address, logo, contact details, etc.
- Start and end dates for the proposed work.
- Description of the work.
- Health and safety contacts.
- Issue date.
- Unique document number.
The method statement should then provide further details relating to the specific work activity. These tend to focus on the type of personal protective equipment (PPE) that will be used for site operatives, as well as any environmental or quality considerations that are of particular importance.
The next section of the method statement will typically provide details such as:
- First aid procedures.
- Staff training required.
- Work permits and other permissions required.
- Scaffolding and working platforms that may be required.
- Site access and egress.
- Materials that will be handled and how they will be stored.
- Construction plant to be used and shut-down procedures.
- Emergency procedures.
- How existing structures will be safeguarded.
The final section of a method statement should set out step-by-step instructions as to how the work activity should be safely carried out and completed.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.